The Federal Highway Administration's second round of quick-release Emergency Relief money goes to the same southwest Colorado routes CDLWire covered Tuesday — US 160 at Wolf Creek Pass and the Piedra River bridge, and CO 151. CDOT's updated damage estimate is $156 million, the state is adding $20 million, and more federal requests are coming as inspections continue.
Summarized from The Trucker.
Southwest Colorado's flood bill has more than doubled, and another round of federal money is on the way to pay for the repairs. According to The Trucker on Nov. 25, the Federal Highway Administration is making an additional $9.1 million in Emergency Relief funds immediately available to the Colorado Department of Transportation for roads and bridges damaged by flooding in the southwest corner of the state. The Colorado Department of Transportation, in its own announcement of the approval, put the updated estimate of flood damage at $156 million — up from an initial estimate of $65 million after the first storm.
The damage came from two back-to-back storm rounds this fall. Severe storms hit the region Oct. 22-25 and again Oct. 31-Nov. 2; the Federal Highway Administration says rainfall reached seven inches during the first half of the event and four inches during the second. The flooding damaged roads and bridges across numerous counties in a rural region that depends on its highways for tourism, agriculture, ranching and outdoor recreation — and, for the communities around Pagosa Springs, on a small number of routes that have no real substitute when they close.
The money is quick-release Emergency Relief funding, the federal program's first installment for restoring essential transportation links after a natural disaster. The U.S. Department of Transportation says this is the second round for this flooding event, following $10.5 million delivered earlier to CDOT and the U.S. Forest Service, bringing the total the department says it has delivered for the event to $19.6 million. CDOT counts the highway quick-release money on its own books: the $9.1 million comes on top of $6.5 million the Federal Highway Administration approved earlier this fall, for $15.6 million in quick-release funding, including $600,000 for county roads — 10 percent of an estimated $6 million in damage to local roads, which CDOT requested on the counties' behalf. The state is adding $20 million in emergency contingency funds authorized by the Colorado Transportation Commission, and CDOT says it will request more federal Emergency Relief funding as damage is verified. The federal highway money is separate from the funding Colorado has requested through a second Presidential Major Disaster Declaration, submitted to the Federal Emergency Management Agency on Nov. 20.
The repair work is concentrated on the routes freight actually uses. CDOT says its maintenance crews, engineers and contractors have been working around the clock on US 160 at Wolf Creek Pass between Pagosa Springs and South Fork, US 160 at the Piedra River bridge between Durango and Pagosa Springs, and Colorado Highway 151 between Ignacio and Pagosa Springs. Those are the same roads CDLWire covered on Tuesday, when CO 151 reopened south of Pagosa Springs after 20 days of round-the-clock rebuilding and became the Piedra River bypass route. CDOT credits the quick-release funding with helping get both Wolf Creek Pass and CO 151 open before Thanksgiving, ending detours that had added hours for Pagosa Springs residents cut off by the closures.
State officials framed the new money as what keeps that pace going into winter. Governor Jared Polis said getting the funding now means construction crews can do more emergency repairs ahead of winter. CDOT Executive Director Shoshana Lew said the dollars let crews and contractors keep working on emergency repairs without delay. At the federal level, Transportation Secretary Sean P. Duffy said the administration is committed to helping Colorado recover and wants roads restored as soon as possible, and Federal Highway Administrator Sean McMaster said the agency will continue to support Colorado until travel is fully restored.
For drivers, the headline number is the one to plan around: $156 million in estimated damage, against the federal and state emergency money identified so far, means this is not a cleanup that ends with the holiday. The estimate itself is expected to change as inspections continue. Expect repair work — and the lane restrictions, detours and slow zones that come with it — to continue on US 160 and the Pagosa Springs-area routes well past Thanksgiving, with winter weather now setting the deadline every crew out there is working against.